Contact Us
Fill in the form below or you can also visit our contact us page.
Implementation is the culmination of all your work in solving a problem and requires careful attention to detail. There are three basic stages involved:
Planning and preparation
Planning and preparation is the key to successful implementation. The more important the problem, or the more complex the actions required to solve it, the more thorough your planning and preparation needs to be to ensure success.
These questions highlight the main features of planning and preparation, which involve:
Constructing a plan of action
Basically, the plan of action describes what actions are required and how they will be implemented to ensure success. Unless the problem is simple or routine, you need to construct a detailed plan of action. This involves systematically identifying and recording the following elements:
1. The actions required
These must be identified fully and precisely, otherwise the results expected will not be achieved. The expected effects of these actions must also be identified, so that you will know when they have been carried out successfully. This part of the plan can be constructed as follows:
The sequence you choose for the various actions and goals is determined by a number of factors. In some situations it may be necessary to complete one action or set of actions before another can begin, eg laying a foundation before building a wall. Actions also have to run consecutively when they each use the same resource to its available capacity. On other occasions actions can run concurrently, such as when each member of a team is assigned a specific piece of equipment to test and evaluate.
With all but the very simplest plans it's wise to use a diagram, to represent the sequence of actions and how they contribute to the overall objective. This helps to show how the actions interact and to reveal areas of possible conflict. Actions should be fitted together as closely as possible, to prevent wastage of resources, while allowing some margin for overrun. To do this you need to prepare a time schedule for the actions.
2. Scheduling the actions
To create a time schedule for the actions, first you identify the time required to complete each action. By representing this information on the diagram you can calculate at what stage, relative to the starting time, each action will commence and finish, and determine the total time required to achieve the objective. Simple plans can be represented by a chart which uses bars to show the sequence and duration of the actions.
More complex plans require a more flexible structure, like a chain diagram or flow chart. Diagrams help you to arrange the actions in a way which makes the best use of time and other resources. In drawing up a schedule. it's important not to be over-optimistic in the time you allow for each action. Additional time is required to accommodate delays and unforeseen obstacles, particularly with actions which must be completed on time or which are susceptible to delays.
3. The resources required
For each action the resources required have to be precisely defined along a number of parameters, including the type, amount and when they are required. Each resource is considered individually:
Time is sometimes overlooked but it can be a key resource in some situations. These can be defined by answering some simple questions.
Manpower may come from within and outside the organisation and can be defined by answering these questions
Money can be defined by answering the questions
Materials may fall into a number of categories, including consumables, raw materials, and equipment (for temporary or permanent use). The material reqirementsse can be defined by answering the questions
Space can be defined by answering these questions
Information may form a part of the manpower resource (eg expert advice or skills) but it can also be a resource in its own right (eg renting a mailing list for a direct mail campaign). To define this resource you need to answer these questions
When you are calculating the resources required to implement a solution it's vital not to under-estimate. A shortage could disrupt implementation completely and possibly incur heavy penalties, eg having to pay a consultant for doing nothing while he's waiting for the installation of a piece of equipment. Sometimes you may have to adapt your plan of action to suit the availability of resources.
Once you have made a complete list of the resource requirements, draw up a schedule of resources,showing how and when they will be requested, from whom, and when and where they are to be delivered.
4. Measures to counter adverse consequences
These have to be included in the plan. Although you have considered the areas of risk and possible side-effects when constructing and evaluating your solution, and adapted it to try to minimise the adverse consequences, you need to identify everything that could go wrong during implementation and devise countermeasures. This includes even minor problems such as a key person being sick.
The steps involved are similar to those used to evaluate and minimise the risks associated with the solution, only more detailed.
There are certain features of a plan of action which can make it more susceptible to something going wrong. To identify these and make provision in your plan to deal with them, you should examine your plan step-by-step and follow these stages:
- timing is crucial (eg with delays, could a deadline be missed?)
- a slippage in timing could bring subsequent actions into conflict (eg so that they simultaneously require the same resource)
- two or more activities coincide (eg will they interfere with each other?)
- there is no way of predicting what may happen (eg because of lack of knowledge or experience)
- there is heavy reliance on facilities or equipment (eg could they fail?) ,
- there is heavy reliance on the cooperation and efforts of people (eg will they perform as required?)
- all available resources in a particular category are being used (eg could an unexpected event require their more urgent use elsewhere?)
- external factors could affect the actions required (eg withdrawal of labour in a national dispute) or the effectiveness of the results (eg a change in market needs)
- what are the effects if this happens?
- how serious are they?
- what is their relative seriousness?
- what is the probability of them happening (low, medium or high)?
Adverse consequences which have the highest probability of occurring combined with the greatest seriousness should be tackled first and every effort made to ensure that provision is made in your plan to counter them effectively. Even if time is short and it requires extensive work, you can only afford to omit minor adverse consequences with a low probability of occurrence. Although problems may not arise during Implementation, if they do your plan must contain appropriate countermeasures which can be taken without jepardising the rest of the plan.
5. Management of the action
Unless the solution is very simple or routine you must specify how the implementation will be monitored and controlled. This enables the manpower to be appropriately led and managed, their progress to be measured at specific intervals, and appropriate action to be taken to correct any variance from the plan. The following steps help to identify how to manage the implementation:
The stages you identify for measuring progress are, in effect, deadlines for achieving specific results. These must be stated as a specific time or date in the overall time schedule. Unspecific or woolly deadlines make implementation difficult to manage and can lead to disaster. The frequency of measuring progress is dependent upon a number of factors:
Provision should also be made to monitor the solution once it has been implemented, so that any unforeseen adverse consequences arising in the long term can be detected. For example, has a change in the system created a bottleneck in processing work, or resulted in undue pressure on one individual or department?
6. Reviewing the plan
Finally, you need to check the plan to ensure that
Drawing up a plan of action is the most crucial stage in ensuring efficient implementation and it must be accurate and thorough. This plan provides a blueprint for the remaining stages of implementation.
Selecting, briefing and training those involved
Your plan of action provides most of the information you require at this stage.
This situation is very similar to having to get your solution implemented successfully. You need to go through the following stages:
Selection involves comparing the skills, qualities and knowledge required for specific tasks with those available amongst individual members of the workforce. By identifying the ideal attributes for carrying out each action effectively - both what is required and what is to be avoided - you can construct a model of the ideal candidate. Selection then consists of finding the best match to this ideal amongst members of the workforce.
Once you have selected appropriate individuals you need to draw up a list of what actions each is required to carry out, the results they will be expected to achieve, and what responsibilities they have for achieving these results.
Frequently there will be at least some aspects of your plan for which the individuals available are not ideally suited. If the discrepancy is large it may be necessary to buy in manpower with the appropriate attributes. However, frequently the shortfall can he overcome by careful briefing or specific training.
Briefing is often the final step before a plan is implemented. As in any other type of communication, it must be planned and executed carefully to ensure that it's effective. The following steps will help you to brief people effectively:
Your instructions should state clearly the responsibilities of each individual and the scope of their authority in carrying out their task. It's important to give a level of authority which enables individuals to use their initiative and not be bound rigidly to the plan. For example, if they foresee a problem arising they need the freedom to act immediately if necessary.
The way you communicate your message is very important. Some individuals may have a different view of the situation and different attitudes to your own, particularly if they have not been involved in finding and evaluating solutions.
Training can be expensive and time-consuming. If people with the appropriate skills are not readily available you need to compare the advantages and disadvantages of training them or buying-in the necessary skills, eg training may provide individuals with skills which are of value in other aspects of their work; hiring a consultant may create a valuable business contact.
Once people have been briefed on what they are required to do and other appropriate resources have been arranged, the plan of action can be implemented.
Implementing and monitoring the action - Once action has been initiated, it has to be supervised and monitored to ensure that the plan is followed accurately, implementing corrective action when necessary. The details of this stage are specified in the plan of action.
Supervising the action ensures that individuals carry out their tasks efficiently according to the plan.
Monitoring progress enables you to identify whether or not the results being achieved are meeting the planned requirements, and if not, why not. A decision can then be made on the action required to put the plan back on course. Reviewing the overall achievement once the plan has progressed significantly will indicate how well it is achieving the objective. If there are major discrepancies it suggests that the plan is inadequate and needs to be revised.
Taking corrective action may involve implementing the appropriate countermeasure laid down in the plan, or taking unplanned action to counter unforeseen problems. For example, if time. has been lost in completing one activity, other activities may have to be completed more quickly than planned in order to meet a deadline. Minor problems which are unlikely to recur may not require any action. Major faults in the plan may make it necessary to abandon implementation if no appropriate corrective action is possible.
These three processes must be maintained until the plan is completed.
Reviewing and analysing the outcome - When the plan has been completed and the solution implemented it is important to measure and analyse its success. This tells you whether the solution has been effective in solving the problem and how useful it will be in solving similar problems in the future. There are three stages
Remember
Read the next article : The Action Plan